Archive for July, 2015

Construction Week 6

Construction Week 6

| July 26, 2015 | 0 Comments

      We now have windows in our new E Franklin Street school! Right now they are boarded up, but soon the glazing for the windows will be installed. Electrical and HVAC work continues on the interior of the building and we expect the drywall to be installed very soon. The exterior stone work, […]

Continue Reading

Construction Week 5

Construction Week 5

| July 17, 2015 | 0 Comments

Things are moving along quickly at our E Franklin Street location. This week the electrical and plumbing rough ins were completed and after passing inspections the dry walls will be going up. All electrical sockets will be placed high up on the walls, over the tops of the shelving holding the Montessori works. We are […]

Continue Reading

New Construction Week 4

New Construction Week 4

| July 7, 2015 | 0 Comments

Construction is going very quickly at our Franklin Street location. The exterior of the building is complete and ready for stucco siding. The entrance looks impressive, even without our logo. the interior wall studs are up defining the classrooms, hallways, office and kitchen. The rooms look light and spacious. This week we picked out wall […]

Continue Reading

Franklin Street Construction

Franklin Street Construction

| July 2, 2015 | 0 Comments

We are so very excited about the progress on our new  E Franklin Street location! Last week the plumbing lines were put in and the concrete slab foundation was laid. This week we saw a lot of progress as the actual building framing went up. Our Franklin Street location will have three classrooms; a Toddler […]

Continue Reading